In an ongoing project, the project sponsor and a manager of the performing organization have conflicts. What would be your comment on this situation?
A、The project manager needs to step in and handle stakeholder expectations. Stakeholders may have different objectives and interests in a project.
B、The project manager needs to step in and handle stakeholder expectations. All stakeholders are supposed to have the same objectives and interests in a project.
C、The project manager will resolve in favor of the project sponsor since he is providing the funds for the project.
D、He project manager will resolve in favor of the manager of the performing organization since they are executing the project and need to be kept in good performance.